Negotiations Update
The Wireless Washtenaw Steering Committee continues to work with 20/20 Communications on finalizing a contract for the deployment of county-wide services. To allow both sides sufficient time to review and discuss the proposed contract, the following new timelines have been adopted:
- Pilot Deployment – October 2006
- Pilot Evaluation – November 2006
- County-Wide Deployment Begins – January 2007
- County-Wide Deployment Complete – December 2007